Case Study: Brampton Park Golf Club

Phase-two greens and tees irrigation at Brampton Park

JK Irrigation delivered the second phase of irrigation renewal at Brampton Park Golf Club after another contractor had completed phase one. The work extended new irrigation across the greens and tees and combined course-wide underground installation with completely renewed pumping and water-storage infrastructure.

Completed pump house and break tank at Brampton Park Golf Club
The completed pump house and break tank at Brampton Park Golf Club.

Phase-two work

  • New greens and tees irrigation across the course
  • Mole-ploughed pipework and cable routes
  • A Hunter irrigation system incorporating selected Rain Bird equipment
  • Construction of the concrete base and new pump house
  • Installation of a break tank to address the club's long-standing suction issues
  • Installation of a new dual pump set
  • Coordination with irrigation designer Giles Wardle

Underground installation across the course

The phase-two network was mole ploughed across the golf course, allowing the greens and tees irrigation to be installed with less open excavation than a fully trenched approach. Routes, existing infrastructure and day-to-day course access still had to be coordinated carefully throughout the works.

The installation formed part of a phased programme. JK Irrigation delivered phase two, including the greens and tees irrigation, pump house, break tank and dual pump set.

Concrete base construction for the new pump house at Brampton Park Golf Club
Construction of the concrete base for the new pump house.
JK Irrigation working across wet winter ground at Brampton Park Golf Club
Course work continuing during wet winter conditions.

Resolving the suction problem

The existing arrangement had a long history of suction difficulties. The phase-two work therefore included a break tank, a new dual pump set and a purpose-built pump house so the water supply, storage and pumping could be treated as one connected system.

JK Irrigation completed the concrete works, built the pump house and installed the new pumping and break-tank arrangement.

Break tank installed at Brampton Park Golf Club
The break tank installed as part of the new water and pumping arrangement.

Winter delivery and design coordination

The phase-two works were completed over approximately two months during the winter. The team worked around localised flooding and difficult ground conditions while maintaining progress across the course.

JK Irrigation worked with irrigation designer Giles Wardle to translate the agreed phase-two design into a practical site installation and connect the greens, tees, controls, pumping and water-storage work into one operating arrangement.